08.03.2024 Wyndham Grand Residences Batumi Gonio. Family Club Installation of the formwork for the floor slab of the 5th floor of Block A continues. In Block B, the formwork for the 3rd stage of the basement walls and floor slab is being installed at the 0.00 level. - European Village