10.07.2024 Wyndham Grand Residences Batumi Gonio. Riviera Block A – on the 3rd floor the walls are being laid with ceramic block. In Block C the floor slab formwork is being assembled. In Block E, fireplaces and staircase reinforcement is in progress. Reinforcement of the floor slab of the infrastructure building is in progress.