Elite Family Residence

1. Finishing works.
— Installation of moldings and skirting boards on the 2nd, 4th floors.
— Puttying and plastering of walls and ceilings in the units, the 3rd- 5th floors.
— Floor tiling in the common areas, the 1st — 4th floors.
— Installation of marble skirting boards on the staircases.
— Floor tiling and bathroom tiling, penthouses.
— Installation of bathtub screens.

2. Facade works.
— Painting of the balconies of the central facade.
— Decorative plastering of balconies of the central facade.
— Priming of balconies of the central facade.

3. Plumbing.
Installation of finishing plumbing in the units.

4. Wiring
Installation of the air ducts for air exchange

5. Installation of staircases railings.

6. Installation of the drywall frames.