Elite Family Residence

1. Installation of porcelain stoneware tiles, penthouses.
— Continued porcelain stoneware tiling in the bathrooms, penthouses.

2. Finishing works.
— Finishing works on the 1st, 3rd, 5th floors.
— Application of developer coat on walls and ceiling, the 1st — 2nd floors.
— Puttying of the 1st and 2nd levels, penthouses.
— Wall plastering in the common areas.

3. Facade works.
— Installation of the decorative elements.
— Priming of balconies on the central facade.
— Decorative plastering of balconies.

4. Plumbing and wiring.

5. Paving with travertine of the balconies’ parapets, penthouses.

6. Elevator installation.
Ongoing works.

7. Installation of polyurethane railings of the central facade, the 3rd floor.

8. Installation of insulation system.
On the terraces.

9. Covering bathtub screens.