Wyndham Grand Batumi Gonio. Aqua
1. Facade works.
— Facade winterization, the 5th, 7th, 11th floors.
— Plastering of facade walls, the 2nd — 20th floors.
2. Installation of utilities systems.
— Water supply and sewage systems are being installed on the 9th, 11th- 17th floors.
— Power supply, the 18th floor.
— Installation of the exhaust ventilation, the 4th -5th floors.
3. Fabrication and installation of steel arches
Balconies on the 19th — 20th floors.
4. Suspended ceiling installation.
On the balconies, the 3rd floor.
5. Waterproofing.
Balconies of the 9th floor.
6. Drywall frame installation.
On the 17th — 19th- floors.
7. Floor screeding.
On the balconies, the 3rd, 19th floors.
8. Installation of the elevator.
Installation of elevator shaft beams on the 20th floor.
9. Mockup construction on the 13th floors.
— Wallpapering.
— Installation of balcony railings on the central facade.
10. Infrastructure building.
Ongoing excavating.