Wyndham Grand Batumi Gonio. Aqua
1. Installation of Engineering Systems
Electrical installation work, 14th floor.
Installation of the water supply system,
Installation of the ventilation system, 20th floor.
2. Facade Works
Thermal insulation of balconies, 3rd, 5th, 12th floors.
3. Installation of Drywall Frame
Installation of guiding frames for drywall partitions,
Sheathing of the frame,
4. Installation of Suspended Ceilings
On the 7th floor.
5. Arch Sheathing
On the 9th,
6. Floor Screed Works
On balconies, 9th, 13th floors.
7. Workshop Works
Manufacturing of embedded parts.
8.Infrastructure Building
Reinforcement of the floor slab.