Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. Installation of electrical system, 12th floor. 2. Waterproofing works, 2nd, 7th floor. Work on the second layer of waterproofing on the balconies. 3. Facade works. Facade insulation on balconies, 13, 14, 19 floors. 4. Works in the workshop. Fabrication of embedded parts. 5. finishing works, 2, 3 floor. Laying of ceramic tiles on the balconies. 6. Masonry works. Installation of racks. 7. Infrastructure building. — Reinforcement of the pool slab. — Installation of formwork. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
Installation of electrical system, 12th floor.

2. Waterproofing works, 2nd, 7th floor.
Work on the second layer of waterproofing on the balconies.

3. Facade works.
Facade insulation on balconies, 13, 14, 19 floors.

4. Works in the workshop.
Fabrication of embedded parts.

5. finishing works, 2, 3 floor.
Laying of ceramic tiles on the balconies.

6. Masonry works.
Installation of racks.

7. Infrastructure building.
— Reinforcement of the pool slab.
— Installation of formwork.