Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
Installation of storm water drainage risers, 14–17 floors.
2. Plastering works.
Plastering of balconies.
3. Masonry works, 10th floor.
Ceramoblock masonry.
4. Installation of gypsum cardboard frame, 7–8 floors.
Installation of partitions.
5. Ceiling installation on the balconies.
On the
6. Installation of elevator shafts.
Completion of work on the installation of lighting.
7. Arrangement of mocap, 3rd floor.
Installation of lighting fixtures.
8. Floor screed works.
Works on the 9th floor.
9. Infrastructure building.
Installation of floor slab formwork, 1st floor.