Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. — Installation of ventilation system. — Installation of electrics, 8th, 15th floor. — Sewerage installation, 10th floor. 2. Facade works. Insulation of the facade, 3–6 floors. 3. 3. Installation of plasterboard frame, 13–14 floors. Installation of partitions. 4. Plastering works, 20th floor. Plastering of balconies. 5. Installation of elevator shafts. Installation of lighting. 6. Waterproofing works. On the roof of the building. 7. Masonry works, 10th floor. Ceramoblock masonry. 8. Infrastructure building. Floor slab formwork on the 2nd floor. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of ventilation system.
— Installation of electrics, 8th, 15th floor.
— Sewerage installation, 10th floor.

2. Facade works.
Insulation of the facade, 3–6 floors. 3.

3. Installation of plasterboard frame, 13–14 floors.
Installation of partitions.

4. Plastering works, 20th floor.
Plastering of balconies.

5. Installation of elevator shafts.
Installation of lighting.

6. Waterproofing works.
On the roof of the building.

7. Masonry works, 10th floor.
Ceramoblock masonry.

8. Infrastructure building.
Floor slab formwork on the 2nd floor.