Wyndham Grand Batumi Gonio. Aqua
Installation of Engineering Systems
Electrical installation work, 3rd, 20th floors.
Installation of the water supply system,
2. Facade Works
Thermal insulation of balconies, 3rd, 5th, 12th floors.
3. Installation of Drywall Frame
Installation of guiding frames for drywall partitions,
Sheathing of the frame,
4. Installation of Suspended Ceilings
On the
5. Arch Sheathing
On the 9th,
6. Workshop Works
Manufacturing of embedded parts.
7. Roof Works
Installation of stands.
8. Infrastructure Building
Reinforcement of the floor slab.