Wyndham Grand Batumi Gonio. Aqua Installation of Engineering Systems Electrical installation work, 3rd, 20th floors. Installation of the water supply system, 3rd-9th floors. 2. Facade Works Thermal insulation of balconies, 3rd, 5th, 12th floors. 3. Installation of Drywall Frame Installation of guiding frames for drywall partitions, 17th-19th floors. Sheathing of the frame, 4th-6th floors. 4. Installation of Suspended Ceilings On the 2nd-7th floors. 5. Arch Sheathing On the 9th, 19th-20th floors. 6. Workshop Works Manufacturing of embedded parts. 7. Roof Works Installation of stands. 8. Infrastructure Building Reinforcement of the floor slab. - European Village

Wyndham Grand Batumi Gonio. Aqua

Installation of Engineering Systems
Electrical installation work, 3rd, 20th floors.
Installation of the water supply system, 3rd-9th floors.

2. Facade Works
Thermal insulation of balconies, 3rd, 5th, 12th floors.

3. Installation of Drywall Frame
Installation of guiding frames for drywall partitions, 17th-19th floors.
Sheathing of the frame, 4th-6th floors.

4. Installation of Suspended Ceilings
On the 2nd-7th floors.

5. Arch Sheathing
On the 9th, 19th-20th floors.

6. Workshop Works
Manufacturing of embedded parts.

7. Roof Works
Installation of stands.

8. Infrastructure Building
Reinforcement of the floor slab.