Wyndham Grand Batumi Gonio. Aqua
1. Facade works.
— Plastering of facade walls, on the 2nd -20th floors.
2. Installation of utilities systems.
— Hot and cold water supply risers are being installed, the 3rd 4th floors.
— Exhaust ventilation installation, the
3. Fabrication and installation of steel arches
Balconies on the 9th,floor.
4. Stained glass window installation, the 2nd — 20th floors.
Ongoing installation of stained glass windows and glazing