Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Plastering of facade walls, on the 2nd — 20th floors.
— Facade winterization, the 4th, 12th, floors.

2. Installation of utilities systems.
— Hot and cold water supply risers are being installed, the 6t — 9th, 14th — 15th floors.
— Exhaust ventilation installation, the 15th -16th floors.
— Wiring on the balconies, the 19th — 20th floors.

3. Fabrication and installation of steel arches.
Balconies on the 9th, 19th floors.

4. Stained glass window installation, the 2nd — 20th floors.
Ongoing installation of stained glass windows and glazing.

5. Mockup construction on the 13th floor.
— Facade winterization.

6. Waterproofing
Balconies of the 16th — 17th floors.

7. Diamond core drilling for engineering openings, the 13th floor.
Marking and drilling of precise openings for the installation of utilities in the future hotel.

8. Floor screeding
The screeding is in progress on the 17th — 18th floors.

10. Drywall frame installation.
— Installation of partitions, the 16th — 20th floors.