Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 15th – 17th floors. This includes the installation of facade elements on balconies. Facade is being winterized. 2. Installation of drywall frames for internal partitions, on the 11th – 20th floors. Thus provides a strong and stable foundation for wall construction. 3. Cladding of decorative columns on the balconies on the 15th – 18th floors. 4. Mockup construction on the 3rd floor. Wiring, plumbing, and finishing works are in progress in the mockup on the 3rd floor. 5. Diamond core drilling for engineering openings on the 8th floor. Marking and drilling of precise openings for the installation of utilities in the future hotel. 6. Ceramic block installation, on the 20th floor. Laying ceramic blocks in accordance with the technology. 7. Cast-in ledges installation, on the 20th floor. It is necessary for stained glass installation. 8. Waterproofing of the balconies on the 7th floor. 9. Screeding on the balconies, on the 11th – 12th floors. Preparation for screeding.