Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 18th – 19th floors. This includes the installation of facade elements on balconies. Facade is being winterized. 2. Installation of drywall frames for internal partitions, on the 11th – 20th floors. Thus provides a strong and stable foundation for wall construction. 3. Cladding of decorative columns on the balconies on the 15th – 18th floors. 4. Water supply and sewer system installation. – Installation of stormwater drainage systems on the 10th floor. – Installation of sewage systems on the 18th – 19th floors. 5. Mockup construction on the 3rd and 13th floors. Wiring and plumbing are in progress in the mockup on the 3rd floor. 6. Diamond core drilling for engineering openings on the 3rd floor. Marking and drilling of precise openings for the installation of utilities in the future hotel. 7. Ceramic block installation, on the 20th floor. Laying ceramic blocks in accordance with the technology. 8. Cast-in ledges installation, on the 18th – 20th floors. It is necessary for stained glass installation. 9. Waterproofing, on the 7th floor.