Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 18th – 19th floors. This includes the installation of facade elements on balconies. Facade is being winterized. The total area of the completed work is 130m2. 2. Glazing of stained glass windows, the 16th floor. Glass installation – 23 units. 3. Installation of cast-in ledges, the 9th floor. The formwork is being installed, concrete is poured, and compacted. Once the concrete has reached the required strength, the formwork is dismantled, and glazing installation begins. 4. Installation of drywall frames for internal partitions, on the 20th floor. Thus provides a strong and stable foundation for wall construction. 5. Cladding of decorative columns on the balconies on the 14th – 18th floors. 12 columns. 6. Water supply and sewer system installation. – Installation of stormwater drainage systems on the 10th floor. The volume of completed works is 3 risers. – Installation of sewage systems on the 18th – 19th floors. The volume of completed works is 12 risers.. 7. Mockup construction on the 3rd and 13th floors. Finishing works in the mockup on the 3rd floor, and finishing sparkling of the ceiling in the mockup on the 13th floor. 8. Ceramic block installation on the 20th floor. Laying ceramic blocks in strict adherence to technological requirements. 9. Ventilation installation on the 3rd floor. Installation of air ducts. 10. Balcony waterproofing on the 12th -13th floors. The total completed area is 75 m2. 11. Diamond core drilling for engineering openings on the 2nd floor. Marking and drilling of precise openings for the installation of utilities in the future hotel – 18 engineering openings. 13. Material delivery. Drywall for installation of drywall framing for internal partitions was unloaded.