Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 3rd, 13th , 19th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames. – Installation of internal partitions, the 3rd–5th, 7th, and 9th floors. – Cladding of ledges, the 8th–9th and 12th floors. – Cladding of columns, 19th floor. 3. Mockup construction on the 3rd, 13th floors. – Painting is in progress on the 3rd floor. – Tiling on the 13th floor. 4. Diamond core drilling for engineering openings on the 7th –8th floors. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems – Assembling and installation of water supply manifolds on the 15th -17th floors. – Hot and cold water supply risers are being installed. 6. Waterproofing of the balconies, on the 7th – 8th floors. 7. Fabrication and installation of steel arches Balconies on the 9th -19th floors. 8. Construction of concrete ledges, 8th –9th floors Formwork and reinforcement for ledges designed to support stained-glass installations.