Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 3rd, 4th, 7th floors. This includes the installation of facade elements on balconies. 2. Installation of drywall frames. – Installation of internal partitions, the 4th – 8th floors. – Cladding of ledges, the 6th –9th floors. 3. Mockup construction on the 3rd, 13th floors. – Painting is in progress on the 3rd floor. 4. Diamond core drilling for engineering openings on the 11th – 12th floors. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems. – Assembling and installation of water supply manifolds. – Hot and cold water supply risers are being installed, the 13th – 14th floors. 6. Waterproofing of the balconies. On the 14th – 15th floors. 7. Fabrication and installation of steel arches Balconies on the 9th -19th floors. 8. Construction of concrete ledges, 3rd –4th floors Formwork and reinforcement for ledges designed to support stained-glass installations. 9. Floor screeding, the 12th floor. The floor screeding is being installed. 10. Elevator shafts are being installed, the 2nd floor. Ceramic block installation. 11. Masonry works, the 20th floor. Ceramic block installation.