Wyndham Grand Batumi Gonio. Riviera.
1. Plastering.
— Plastering of inner walls in Blocks E, B the 1st- 3rd floors.
2. Block A. Facade works.
— Facade plastering.
3. Block B. Installation of staircases.
Formwork installation for the staircases.
4. Block A. Masonry works.
Ceramic block installation.
5. Infrastructure building.
Formwork removal.