Wyndham Grand Batumi Gonio. Villas.1. Continuation of column reinforcement, Villas 8 and 9. It ensures the strength and stability of the columns, preventing deformation and enhancing the building’s durability. 2. Removal of formwork from the slab, Villas 1 and 4. Removal of formwork after concrete hardening to complete the structure and prepare for the next construction stage. 3. Continuation of stair formwork installation, Villa 5. The installation of formwork to shape the staircase, essential for concrete pouring and forming its structure. 4. Waterproofing of internal foundation walls, Villa 16. It protects the foundation from moisture penetration, preventing concrete deterioration and enhancing the building’s longevity. 5. Installation of sewer outlets at Villas 14 and 15. 6. Backfilling of foundation walls at Villas 14 and 15.