Wyndham Grand Batumi Gonio. Villas.
1. Masonry works, villa 1, 2, 4.
Ceramoblock masonry of external walls.
2. Works on dismantling the formwork
— floor slab II floor, villa 6,
— columns II floor, villas 10, 11.
Removal of formwork after concrete curing to complete the structure and prepare for the next stage of construction.
3. Assembly of the formwork for the stairs from the 1st to the 2nd floor, villa 11, 12, 13.
Installation of formwork to create the mold, which is necessary to pour the concrete and form the structure.
4. Fabrication of the reinforcement frames of the columns of the 2nd floor, villa 13, 14.
5. Fabrication of embedded parts.