26.02.2024 Wyndham Grand Residences Batumi Gonio. Family Club Concreting of the 1st stage of columns was carried out on the 4th floor of Block A, reinforcement of the 2nd stage of columns is in progress. Dismantling of the basement wall formwork is underway in Phase 1 of Block B, and wall reinforcement continues in Phase 2. - European Village

26.02.2024 Wyndham Grand Residences Batumi Gonio. Family Club Concreting of the 1st stage of columns was carried out on the 4th floor of Block A, reinforcement of the 2nd stage of columns is in progress. Dismantling of the basement wall formwork is underway in Phase 1 of Block B, and wall reinforcement continues in Phase 2.