Wyndham Grand Batumi Gonio. Aqua1. Diamond drilling for engineering openings, floors 10th, 17th. Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained glass. The construction of ledges for stained glass along with the stained glass installation. This ensures light permeability and improves thermal and sound insulation for hotel rooms. 3. Facade work, the 3rd , 6th , 8th floors. This includes the installation of facade elements on balconies. 4. Ceramic block Installation, 20th floor. Installation of ceramic blocks in accordance with the technology, ensuring wall alignment and verticality. Checking all joints and angles for compliance with the design specifications. 5. Mock-up construction, 12th floor. This allows for the visualization and verification of the design and materials for the hotel room, The painting and ceramic granite installation are in progress in the bathrooms. 6. Installation of plumbing and sewage systems. Installation of the sewerage system and sealing of sewer risers on the 5th to 9th floors. Installation of the stormwater drainage system on the 13th to 20th floors. 7. Installation of decorative steel columns, floors 10th, 17th , 18th.