Wyndham Grand Batumi Gonio. Aqua1. Diamond drilling for engineering openings, the 10th,17th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained glass. The construction of ledges for stained glass along with the stained glass installation. This ensures light permeability and improves thermal and sound insulation for hotel rooms. 3. Facade work, the 12th -14th floors. This includes the installation of facade elements on balconies. 4. Ceramic block Installation, 20th floor. Installation of ceramic blocks in accordance with the technology, ensuring wall alignment and verticality. Checking all joints and angles for compliance with the design specifications. 5. Installation of plumbing and sewage systems. The installation of the sewerage system on the 7th – 9th floors and sealing of sewer risers on the 8th – 13th floors are in progress. The installation of the stormwater drainage system on the 11th – 20th floors is underway. 6. Installation of decorative steel columns, floors 18th -20th. The columns are being fabricated and installed. The installation of drywall frames for interior partitions is ongoing on the 2nd , 8th , 11th , 17th, and 18th floors.