Wyndham Grand Batumi Gonio. Aqua1. Diamond drilling for engineering openings, the 19th – 20th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained glass. The construction of ledges for stained glass along with the stained glass installation. This ensures light permeability and improves thermal and sound insulation for hotel rooms. 3. Facade work, the 14th -15th floors. This includes the installation of facade elements on balconies. 4. Mock-up construction, the 12th floor. This enables visualization and testing of design and materials for the hotel unit. Tile grouting. 5. Installation of plumbing and sewage systems. The installation of the sewerage system on the 4th – 5th floors continues. The installation of the stormwater drainage system on the 18th – 20th floors is underway. 6. Ceramic block Installation, 20th floor. Installation of ceramic blocks in accordance with the technology. 7. Installation of decorative steel columns, floor 10th. The columns are being fabricated and installed The installation of drywall frames for interior partitions is underway on the 4th, 11th, 15th – 18th floors.