Wyndham Grand Batumi Gonio. Family Club. Block A 1. Plastering work. — Plastering of slopes, 3rd floor. — Plastering of the facade, installation of beacons for plastering. 2. Finishing work. Installation of ceramic granite floor tiles on the balcony. 3. Facade work. Facade cladding with clinker tiles. Block B. 1. Masonry work. Ceramic block masonry, 5th floor. - European Village

Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Plastering work.
— Plastering of slopes, 3rd floor.
— Plastering of the facade, installation of beacons for plastering.

2. Finishing work.
Installation of ceramic granite floor tiles on the balcony.

3. Facade work.
Facade cladding with clinker tiles.

Block B.
1. Masonry work.
Ceramic block masonry, 5th floor.