Wyndham Grand Batumi Gonio. Family Club. Block A 1. Plastering work. Plastering of slopes. 2. Facade work. — Facade and slope cladding with clinker tiles. — Plastering of the facade. 3. Installation of plasterboard frame. Covering of ceiling frame. 4. Installation of metal arches on balconies. Block B. 1. Masonry work, 5th floor. Laying ceramic blocks. 2. Installation of stained glass structures. Installation of stained glass and glazing. - European Village

Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Plastering work.
Plastering of slopes.

2. Facade work.
— Facade and slope cladding with clinker tiles.
— Plastering of the facade.

3. Installation of plasterboard frame.
Covering of ceiling frame.

4. Installation of metal arches on balconies.

Block B.
1. Masonry work, 5th floor.
Laying ceramic blocks.

2. Installation of stained glass structures.
Installation of stained glass and glazing.