Wyndham Grand Batumi Gonio. Family Club.
Block A
1. Plastering work.
— Plastering of slopes, 1st and 4th floors.
— Plastering walls, 2nd floor.
2. Facade work.
— Facade and slope cladding with clinker tiles.
— Facade insulation.
3. Plasterboard frame installation work, 3rd floor.
Ceiling frame covering.
4. Waterproofing work.
Preparatory work for waterproofing terraces.
5. Installation of stained glass structures.
Installation of
Block B.
1. Installation of stained glass structures.
Installation of stained glass windows.