Wyndham Grand Batumi Gonio. Family Club.
Block A
1. Plastering work.
— Plastering of slopes, 1st and 4th floors.
— Plastering of walls, 2nd floor.
2. Facade work.
— Facade and slope cladding with clinker tiles.
— Facade insulation, reinforcement installation on the facade.
3. Plasterboard frame installation work, 3rd floor.
Ceiling frame covering.
4. Waterproofing work.
Preparatory work for waterproofing terraces.
5. Installation of stained glass structures.
Installation of
Block B.
1. Installation of monolithic sides.
For the installation of stained glass structures.