Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. — Electrical work. — Plumbing work. — Installation of fire extinguishing system. 2. Installation of elevator shafts. Installation of elevator equipment. 3. Plastering work. Installation of decorative plaster on balconies. 4. Installation of plasterboard frame. Covering of ceiling frame. 5. Finishing work. Laying tiles on balconies. 6. Drilling engineering holes. For subsequent installation of engineering systems. 7. Infrastructure building. — Installation of formwork for the 4th floor slab. — Laying ceramic blocks. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.

— Electrical work.

— Plumbing work.

— Installation of fire extinguishing system.

2. Installation of elevator shafts.

Installation of elevator equipment.

3. Plastering work.

Installation of decorative plaster on balconies.

4. Installation of plasterboard frame.

Covering of ceiling frame.

5. Finishing work.

Laying tiles on balconies.

6. Drilling engineering holes.

For subsequent installation of engineering systems.

7. Infrastructure building.

— Installation of formwork for the 4th floor slab.

— Laying ceramic blocks.