Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. — Electrical work. — Plumbing work. 2. Facade work. Facade texturing. 3. Plastering work. Installation of decorative plaster on balconies. 4. Ceiling installation work. Installation of ceiling frames on balconies. 5. Finishing work. Laying tiles on balconies on the 19th floor. 6. Drilling engineering holes. For subsequent installation of engineering systems. 7. Infrastructure building. — Reinforcement of vertical structures on the 5th floor. — Laying ceramic blocks. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.

— Electrical work.

— Plumbing work.

2. Facade work.

Facade texturing.

3. Plastering work.

Installation of decorative plaster on balconies.

4. Ceiling installation work.

Installation of ceiling frames on balconies.

5. Finishing work.

Laying tiles on balconies on the 19th floor.

6. Drilling engineering holes.

For subsequent installation of engineering systems.

7. Infrastructure building.

— Reinforcement of vertical structures on the 5th floor.

— Laying ceramic blocks.