Wyndham Grand Batumi Gonio. Family Club. Block A 1. Finishing works. Laying porcelain stoneware on balconies. 2. Plastering work. — Application of decorative plaster on balconies and stained glass slopes. — Plastering of walls. 3. Facade work. Grouting of clinker tile joints on the facade. Block B 1. Plastering work. Plastering interior walls. 2. Facade work. Plastering the facade. 3. Installation of elevator shafts. Formwork for elevator shaft portal beams. 4. Installation of ceilings. Installation of ceiling frames on balconies. 5. Drilling of engineering holes. For subsequent installation of engineering systems. 6. Installation of stained glass structures. Installation of stained glass and glass. - European Village

Wyndham Grand Batumi Gonio. Family Club.

Block A

1. Finishing works.

Laying porcelain stoneware on balconies.

2. Plastering work.

— Application of decorative plaster on balconies and stained glass slopes.

— Plastering of walls.

3. Facade work.

Grouting of clinker tile joints on the facade.

Block B

1. Plastering work.

Plastering interior walls.

2. Facade work.

Plastering the facade.

3. Installation of elevator shafts.

Formwork for elevator shaft portal beams.

4. Installation of ceilings.

Installation of ceiling frames on balconies.

5. Drilling of engineering holes.

For subsequent installation of engineering systems.

6. Installation of stained glass structures.

Installation of stained glass and glass.