Wyndham Grand Batumi Gonio. Aqua.
1. Installation of engineering systems.
— Electrical work, laying electrical cables, 7th floor.
— Plumbing work, drainage installation, 18th floor.
— Installation of air conditioning pipes.
2. Installation of plasterboard frame, 13th floor.
Installation of frame for
3. Finishing work, 8th and 18th floors.
Laying tiles on balconies.
4. Plastering work.
Plastering balconies.
7. Installation of a panoramic elevator.
Installation of formwork for panoramic elevator balconies.
8. Waterproofing work, 18th floor.
Application of coating waterproofing on balconies.
9. Infrastructure building.
— Reinforcement of vertical structures, 8th floor.
— Ceramic block masonry, 4th floor.