Monthly construction report Wyndham Grand Batumi Gonio. Aqua September 2025 September saw dynamic progress on all fronts of the project: from the construction of monolithic structures to the detailed design of facades and engineering systems. Dozens of processes are being carried out simultaneously on the sites, which allows us to maintain a high pace. ​​- Installation of engineering systems Work is underway on the installation of hot and cold water supply systems: installation of water outlets and smart boxes. Installation of a sewage system: connection of a washbasin and VRF drainage, connection of a shower drain. Installation of the air conditioning system: laying horizontal cooling lines on 5 floors. Installation of water fire extinguishing system pipelines is underway. Work is underway on electrical lighting and power supply. Work is being carried out on the installation of low-current cable systems. ​​- Installation of stained glass structures Installation of stained glass windows on the 10th floor is underway: frames are being assembled and preparations are being made for installation. ​​- Installation of balconies in units Work is underway on the installation of balconies in units. Porcelain tile is being laid on 4 floors, ceilings are being reinforced and faced with concrete on 6 floors, and decorative plaster is being applied to the walls and ceilings on 6 floors. ​​- Installation of plasterboard frame Work continues on cladding the walls of the units with plasterboard sheets and installing insulation in the partition frame. ​​- Facade work Work continues on plastering the facade. — Elevator installation Elevator equipment installation work: elevator power cable laid, elevator doors being installed — Infrastructure building work Walls, columns, and floor slabs for floors 1–8 completed. Ceramic block masonry has been completed on the exterior walls of floors 1–4 and is continuing on floor 5. - European Village

Monthly construction report
Wyndham Grand Batumi Gonio. Aqua
September 2025

September saw dynamic progress on all fronts of the project: from the construction of monolithic structures to the detailed design of facades and engineering systems. Dozens of processes are being carried out simultaneously on the sites, which allows us to maintain a high pace.

​​- Installation of engineering systems
Work is underway on the installation of hot and cold water supply systems: installation of water outlets and smart boxes.
Installation of a sewage system: connection of a washbasin and VRF drainage, connection of a shower drain.
Installation of the air conditioning system: laying horizontal cooling lines on 5 floors.
Installation of water fire extinguishing system pipelines is underway.
Work is underway on electrical lighting and power supply. Work is being carried out on the installation of low-current cable systems.
​​- Installation of stained glass structures
Installation of stained glass windows on the 10th floor is underway: frames are being assembled and preparations are being made for installation.
​​- Installation of balconies in units
Work is underway on the installation of balconies in units. Porcelain tile is being laid on 4 floors, ceilings are being reinforced and faced with concrete on 6 floors, and decorative plaster is being applied to the walls and ceilings on 6 floors.
​​- Installation of plasterboard frame
Work continues on cladding the walls of the units with plasterboard sheets and installing insulation in the partition frame.
​​- Facade work
Work continues on plastering the facade.
— Elevator installation
Elevator equipment installation work: elevator power cable laid, elevator doors being installed
— Infrastructure building work
Walls, columns, and floor slabs for floors 1–8 completed.
Ceramic block masonry has been completed on the exterior walls of floors 1–4 and is continuing on floor 5.