Monthly construction report Wyndham Grand Batumi Gonio. Family Club September 2025 In September 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project. Block A — During the installation of the roofing system, vapor barrier was installed, insulation with a slope was laid, and PVC membrane is being installed. — Work is underway on the installation of stained glass profiles, double-glazed windows, and the sealing of installation joints. — Work is underway on the installation of upper waterproofing coating on balconies on floors 1–4. — Work is underway on the installation of porcelain stoneware on balconies on floors 1–4. — Plastering work is underway: reinforcement for decorative plaster application, plastering work on the outside of balconies, plastering work on the facade of the block. — Facade work continues — installation of mineral wool, reinforcement and plastering, priming for the application of decorative plaster — Work is underway on the installation of clinker tiles on the facade Block B — Monolithic work is underway: filling holes in floor slabs, drilling engineering holes in floor slabs. — During the installation of elevator shafts: installation of elevator embedments, masonry of elevator portals with gas silicate blocks has been completed. — Work has been completed on the installation of stained glass profiles and double-glazed windows on the 2nd and 3rd floors. — Work has been completed on the installation of the frame and cladding of storm sewer risers on balconies. — Work is underway on the installation of ceiling frames on balconies. — Work is underway on plastering the terraces and interior walls. — Work continues on installing mineral wool on the facade. - European Village

Monthly construction report
Wyndham Grand Batumi Gonio. Family Club
September 2025

In September 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project.

Block A
— During the installation of the roofing system, vapor barrier was installed, insulation with a slope was laid, and PVC membrane is being installed.
— Work is underway on the installation of stained glass profiles, double-glazed windows, and the sealing of installation joints.
— Work is underway on the installation of upper waterproofing coating on balconies on floors 1–4.
— Work is underway on the installation of porcelain stoneware on balconies on floors 1–4.
— Plastering work is underway: reinforcement for decorative plaster application, plastering work on the outside of balconies, plastering work on the facade of the block.
— Facade work continues — installation of mineral wool, reinforcement and plastering, priming for the application of decorative plaster
— Work is underway on the installation of clinker tiles on the facade
Block B
— Monolithic work is underway: filling holes in floor slabs, drilling engineering holes in floor slabs.
— During the installation of elevator shafts: installation of elevator embedments, masonry of elevator portals with gas silicate blocks has been completed.
— Work has been completed on the installation of stained glass profiles and double-glazed windows on the 2nd and 3rd floors.
— Work has been completed on the installation of the frame and cladding of storm sewer risers on balconies.
— Work is underway on the installation of ceiling frames on balconies.
— Work is underway on plastering the terraces and interior walls.
— Work continues on installing mineral wool on the facade.