Monthly construction report
Wyndham Grand Batumi Gonio. Family Club
September 2025
In September 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project.
Block A
— During the installation of the roofing system, vapor barrier was installed, insulation with a slope was laid, and PVC membrane is being installed.
— Work is underway on the installation of stained glass profiles,
— Work is underway on the installation of upper waterproofing coating on balconies on floors 1–4.
— Work is underway on the installation of porcelain stoneware on balconies on floors 1–4.
— Plastering work is underway: reinforcement for decorative plaster application, plastering work on the outside of balconies, plastering work on the facade of the block.
— Facade work continues — installation of mineral wool, reinforcement and plastering, priming for the application of decorative plaster
— Work is underway on the installation of clinker tiles on the facade
Block B
— Monolithic work is underway: filling holes in floor slabs, drilling engineering holes in floor slabs.
— During the installation of elevator shafts: installation of elevator embedments, masonry of elevator portals with gas silicate blocks has been completed.
— Work has been completed on the installation of stained glass profiles and
— Work has been completed on the installation of the frame and cladding of storm sewer risers on balconies.
— Work is underway on the installation of ceiling frames on balconies.
— Work is underway on plastering the terraces and interior walls.
— Work continues on installing mineral wool on the facade.