Monthly Construction Report Wyndham Grand Batumi Gonio. Riviera November 2025 In November 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project. Block A — Work is underway on the installation of upper waterproofing on the balconies of the townhouses. — Work is being completed on covering the chimney and drainage boxes with concrete panels. — Decorative facade elements have been ordered, delivered, and installed. — Work is underway on the installation of a monolithic staircase railing. — Work continues on the installation of mats and pipes for underfloor heating. — Work is underway on the installation of electrical lighting and power supply in the townhouses, as well as the installation of facade lighting. Blocks B and C — Work is underway on installing upper waterproofing on the balconies in the townhouses. — Chimneys have been installed on Block C. — Work is underway on installing plasterboard frames for interior partitions and covering the partition frames. ​​- Work has begun on the installation of mats and pipes for underfloor heating. ​​- Work is underway on the installation of electrical lighting and power supply in the townhouses. Block E — Work has been completed on the installation of upper waterproofing on the balconies of the townhouses. — Decorative facade elements have been ordered, delivered, and installation has begun. — Work has been completed on the installation of mats and pipes for underfloor heating. Infrastructure building — Membrane waterproofing has been installed on the roof. — Facade work has been completed on the installation of mineral wool and reinforcement of mineral wool. Work is underway on priming before applying decorative plaster. Landscaping The excavation for the pool has been completed. Monolithic work on the construction of the pool foundation has begun and is continuing. - European Village

Monthly Construction Report
Wyndham Grand Batumi Gonio. Riviera
November 2025

In November 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project.
Block A
— Work is underway on the installation of upper waterproofing on the balconies of the townhouses.
— Work is being completed on covering the chimney and drainage boxes with concrete panels.

— Decorative facade elements have been ordered, delivered, and installed.
— Work is underway on the installation of a monolithic staircase railing.
— Work continues on the installation of mats and pipes for underfloor heating.
— Work is underway on the installation of electrical lighting and power supply in the townhouses, as well as the installation of facade lighting.

Blocks B and C
— Work is underway on installing upper waterproofing on the balconies in the townhouses.
— Chimneys have been installed on Block C.
— Work is underway on installing plasterboard frames for interior partitions and covering the partition frames.
​​- Work has begun on the installation of mats and pipes for underfloor heating.
​​- Work is underway on the installation of electrical lighting and power supply in the townhouses.

Block E
— Work has been completed on the installation of upper waterproofing on the balconies of the townhouses.
— Decorative facade elements have been ordered, delivered, and installation has begun.
— Work has been completed on the installation of mats and pipes for underfloor heating.

Infrastructure building
— Membrane waterproofing has been installed on the roof.
— Facade work has been completed on the installation of mineral wool and reinforcement of mineral wool. Work is underway on priming before applying decorative plaster.

Landscaping
The excavation for the pool has been completed. Monolithic work on the construction of the pool foundation has begun and is continuing.