01.12.2023 Wyndham Grand Residences Batumi Gonio. Aqua Reinforcement of the floor slab continues on the 18th construction (17th hotel) floor. Ceramic block walls are being laid on floors 8 (7) and 9 (8). - European Village

01.12.2023 Wyndham Grand Residences Batumi Gonio. Aqua Reinforcement of the floor slab continues on the 18th construction (17th hotel) floor. Ceramic block walls are being laid on floors 8 (7) and 9 (8).