13.12.2023 Wyndham Grand Residences Batumi Gonio. Riviera In the 1st half of Block A, the reinforcement of the floor slab of the 3rd floor has been completed. Excavation work continues in Block B. In Block E, work is underway on the ceramic block parapet. - European Village

13.12.2023 Wyndham Grand Residences Batumi Gonio. Riviera In the 1st half of Block A, the reinforcement of the floor slab of the 3rd floor has been completed. Excavation work continues in Block B. In Block E, work is underway on the ceramic block parapet.