14.12.2023 Wyndham Grand Residences Batumi Gonio. Riviera In Block A, reinforcement of the floor slab of the 3rd floor continues in the first half and concreting of the floor slab of the 3rd floor has been carried out in the second half. Excavation work is underway in Block B. In Block E, the masonry of the parapet with ceramic block continues. - European Village

14.12.2023 Wyndham Grand Residences Batumi Gonio. Riviera In Block A, reinforcement of the floor slab of the 3rd floor continues in the first half and concreting of the floor slab of the 3rd floor has been carried out in the second half. Excavation work is underway in Block B. In Block E, the masonry of the parapet with ceramic block continues.