24.01.2024 Wyndham Grand Residences Batumi Gonio.Family Club In Block A, after concreting of the 2nd stage of columns, the dismantling of their formwork is underway, and the installation of formwork for the 3rd floor floor slab has started. In Block B, preparations are underway for the concreting of the foundation slab. - European Village

24.01.2024 Wyndham Grand Residences Batumi Gonio.Family Club In Block A, after concreting of the 2nd stage of columns, the dismantling of their formwork is underway, and the installation of formwork for the 3rd floor floor slab has started. In Block B, preparations are underway for the concreting of the foundation slab.