16.05.2024 Wyndham Grand Residences Batumi Gonio. Family Club On the 1st floor of block A, the laying of walls with ceramic block continues, above the 5th floor the reinforcement of the floor slab is in progress. Reinforcement of the floor slab is being done on the 3rd floor of the block.