21.05.2024 Wyndham Grand Residences Batumi Gonio. Family Club Block A — concreting of the roof slab has been carried out. The monolithic frame work in the block is complete. The laying of walls with ceramic block on the 1st floor continues. Block B — reinforcement and erection of formwork for columns of the 3rd floor.