02.05.2024 Wyndham Grand Residences Batumi Gonio. Riviera On the 2nd floor of Block A, masonry walls continue to be laid with ceramic block. In Block B, the floor slab formwork is being dismantled. Reinforcement of the foundation slab continues in Block C. Excavation works are being carried out in Block D.