02.12.2023 Wyndham Grand Residences Batumi Gonio. Riviera On the first floor of the first half of Block A, dismantling of the floor slab formwork continues and reinforcement of the columns is being carried out. Installation of reinforcement cages of vertical structures in the second half of the block is in progress. The concreting of the columns has taken place. Excavation work continues in Block B.