04.09.2023 Wyndham Grand Residences Batumi Gonio. Aqua The installation of formwork for the slab on the 14th construction (13th hotel) floor is underway. The construction of ceramic block walls continues on the 2nd & 3rd construction (1st & 2nd hotel) floors. The construction material is being delivered to the 4th (3rd) floor.