07.04.2024 Wyndham Grand Residences Batumi Gonio. Riviera Ceramic block wall masonry continues in Block A. In Block B, the floor slab formwork is being assembled. Excavation works are being carried out in Block D. Installation of the formwork for the vertical structures of the infrastructure building continues.