07.09.2024 Wyndham Grand Residences Batumi Gonio. Riviera In Block A, monolithic boards for stained glass windows and drilling of holes in the floor slab are being installed. In Block B - laying of ceramic block (first floor) and fireplaces, construction of a temporary staircase to the roof. In Block C - fencing and dismantling of formwork. In the infrastructure building - installation of formwork for transoms and columns. - European Village

07.09.2024 Wyndham Grand Residences Batumi Gonio. Riviera In Block A, monolithic boards for stained glass windows and drilling of holes in the floor slab are being installed. In Block B – laying of ceramic block (first floor) and fireplaces, construction of a temporary staircase to the roof. In Block C – fencing and dismantling of formwork. In the infrastructure building – installation of formwork for transoms and columns.