Wyndham Grand Batumi Gonio. Aqua Installation of stained glass windows continues at the site. Installation of formwork, framing of balconies with reinforced concrete edges, installation of decorative boxes on balconies, dusting of ceilings, geodesic works, anti-corrosion works (metal painting), lifting of double-glazed windows to the floors, installation of lift shaft coverings (preparation for installation of lift equipment). On the first floor is the installation of plasterboard frame of internal partitions. On the 10th floor – diamond drilling of engineering holes. In the mockup on the third floor is the installation of plumbing, in the mockup on the 12th floor – installation of partitions.