08.02.2024 Wyndham Grand Residences Batumi Gonio. Riviera Dismantling of the floor slab formwork is underway in Block A. Excavation works are being carried out in Block B. Reinforcement of the 2nd stage of the foundation slab is underway. In Block E, the walls are masonry with ceramic block.