09.01.2024 Wyndham Grand Residences Batumi Gonio. Riviera Block A: Installation of the roof slab formwork continues in the first half. In the second half, dismantling of the roof slab formwork began. Block B: Excavation work is underway. Block E: Walls and partitions are being laid on the floors.