11.12.2023 Wyndham Grand Residences Batumi Gonio. Aqua Installation of the formwork for the floor slab of the 19th construction (18th hotel) floor has been completed. Reinforcement of the slab has begun. Wall masonry work on the 11th (10th) floor continues.